Job Profiles

Here are a few examples of recent projects.

Projects: Lee Station
Date: 1st Nov 2011
Programme: Riser Wall Rebuild
Overview: We were called to attend a fault where the riser wall had spilt on the lower section along the courses of the wall.
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Farningham Road Station - Waiting Shelter Re-Build
Date: 1st Nov 2011
Programme: 2 Weeks
Overview: The 2 main beams to the London End of the canopy had completely rotten through as they exit the station building roof, under the box gutter construction. The box gutter in the area that we had exposed had also rotted beyond any repair and required re
The Job Sheet: Click here to Download the JobSheet PDF

Projects: The Hastings Accademy
Date: 6th Aug 2011
Programme: Phase 1 – 10 Weeks - Phase 2 – 8 Weeks 2013
Overview: To remove the Asbestos containing materials under semi, and fully
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Removal of Surrey Canal Road Footbridge
Date: 16th May 2011
Programme: 10 Hours
Overview: Econ Construction Limited have gained a contract to carry out the demolition and
The Job Sheet: Click here to Download the JobSheet PDF

Projects: London Underground Mid Tunnel Ventilation Project – Redundant Vent Shaft Fan Dismantling & Removal
Date: 16th Nov 2010
Programme: 3 Months
Overview: · Dismantling & Removal of All Redundant Plant including Fan, Controls and Ducting
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Tate & Lyle Europe – Building Deconstruction
Date: 6th Aug 2010
Programme: Four Weeks
Overview: Works were undertaken for Tate and Lyle Europe decommissioning redundant process building that was to be re modernised.
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Lineside Building & Sale Reel Warehouse Demolition Adjacent to Live Railway Line
Date: 1st Jan 2010
Programme: 4 Months
Overview: To Demolish Line side Railway Building, and Adjacent Sale Reel Warehouse
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Redundant Pipe Removal Including Asbestos Lagged Pipework
Date: 30th Jun 2009
Programme: 3 Months
Overview: To cut and remove redundant pipe work across the River Medway, to also decontaminate the asbestos lagged pipe work then cut and remove.
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Demolition of Brimsdown Signal Box
Date: 20th May 2009
Programme: 52 Hour Possession (Finished in 14 Hours)
Overview: To Demolish the Redundant Trackside Signal Box
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Asbestos Removal From The Morgue at Queen Mary's Hospital Sidcup
Date: 1st May 2009
Programme: 1 Week
Overview: To remove AIB ceiling refrigerator lobby and viewing room
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Clapham Common Vent Shaft Project
Date: 1st May 2009
Programme: 3 Months
Overview: Asbestos Removal inc all Redundant Cable and Electrical Equipment
The Job Sheet: Click here to Download the JobSheet PDF

Projects: Access Stairs and Canopy Dismantle and Removal from Platform 11 & 12 at
Date: 1st May 2009
Programme: 12 Hr Possesion
Overview: To remove the Asbestos Cement roof sheets, then hot cut and dismantle the
The Job Sheet: Click here to Download the JobSheet PDF