CASE STUDY:

Bridge Demolition - Abbey Wood

Services: Bridge demolition; waste and environmental management; site mobilisation and demobilisation; protection of working culvert; road traffic management.

Project duration: Bank holiday weekend

Summary: Econ was commissioned to demolish and clear a concrete footbridge spanning a four lane highway. Timing was critical to ensure that disruption to traffic and local residents was kept to a minimum. Working ‘round the clock’ over a four day weekend period the Econ team successfully demolished and disposed of a large concrete structure in a controlled, efficient and safe operation. A carefully planned convoy approach ensured that all waste material was removed and recycled in the most environmentally friendly way possible.

Staffing requirements: Careful and detailed planning was essential and the works were overseen and coordinated by one of our highly experienced project managers. Key staff included demolition technicians, and a team of waste removal and recycling operatives. By using our own material recycling facilities and pre-selected and vetted sites we were able to clear a large quantity of waste arising from the demolition over the four day period.

Equipment/Plant Used: 1 x 35t 360 Excavator with a Concrete Cruncher attachment, 3 x 23t 360 Excavators with Breaker and Grab attachments, 1 x 15t 360 Excavator with Selecta Grab attachment and 1 x 360 Telehandler.

Case Studies
Woking Station Canopy

Econ were employed as a principle Contractor to plan, design and remove the canopy outside Woking Railway Station.

 

READ MORE
Bridge Demolition - Abbey Wood

Econ was commissioned to demolish and clear a concrete footbridge spanning a four lane highway. Timing was critical to ensure that disruption to traffic and local residents was kept to a minimum.

READ MORE
Holland Lane East Bridge Demolition

Econ was called in to demolish the Holland Lane East road bridge, which passes over the railway tracks on the Oxted to Edenbridge line. Because of the need to minimise disruption to train services Econ were allowed a 52 hour window of access to the rail and road site and immediate surroundings.

READ MORE
Loaders Enabling Works, Silvertown

 Econ were contracted to carry out the complete enabling works package at Tate & Lyle, we carried out all the design works, service isolations and diversion, all surveys including Ground Radar & Demolition Asbestos Surveys

READ MORE
Coram Fields

What the client said:

“We found Econ to be talented and professional. We recently employed them to undertake some regeneration work to help us prepare for the building of our new Queen Elizabeth II Centre. Our experience of working with them was excellent. They were conscientious and efficient when working to a tight deadline and we have no hesitation recommending them for other projects.”

READ MORE
TFL Rolling Stock Disposal

Summary: Econ was retained to dismantle and dispose of redundant rolling stock for a number of TfL’s rail subsidiaries, as part of the company’s vital programme of network upgrading and modernisation.

READ MORE
The Grove School

 

Econ carried out the isolation and removal of all services, the removal of asbestos then the demolition and clearance of the complete site.

READ MORE
Harrow Manorway

Econ were contracted by FM Conway to carry out the design and demolition of Harrow Manorway footbridge in Thamesmead, South East London.

READ MORE
Licensable Asbestos Removal - Roof Void

What the client said:

"Professional, tidy and - what I like most - independent; we barely knew they were here."

READ MORE
WHAT OUR CLIENTS SAY
We found Econ to be talented and professional. We recently employed them to undertake some regeneration work to help us prepare for the building of our new Queen Elizabeth II Centre. Our experience of working with them was excellent. They were conscientious and efficient when working to a tight deadline and we have no hesitation recommending them for other projects.
read more...
Coram
I have worked with Econ on many projects within London Underground and Network Rail infrastructure. Econ have always been very proactive in their approach to the projects and have worked collaboratively with my teams from the very early stages. I would definitely recommend them to others
read more...
Morgan Sindall
Also evident was the pride the staff have in what they do and the care they take to work safely at all times and offer the best service possible to their clients
read more...
BAE Systems
OUR CHARITY WORK

The Econ team is very active and always looking for ways to raise money for these excellent causes, fielding competitors in challenges such as the London Marathon, the London to Brighton Cycle race and the Killarney Adventure race!

Kent Website Design by SPLAT WEB WORKS